    a and b can do a piece of work in 60 days, b and c can do it in 100 days, a and c can do it in 75 days. in how many days b alone can do it?

    Mohammed

    Guys, does anyone know the answer?

    get a and b can do a piece of work in 60 days, b and c can do it in 100 days, a and c can do it in 75 days. in how many days b alone can do it? from screen.

    [Solved] A and B can complete a work in 60 days, B and C complete it

    Given: A + B can complete in 60 Days B + C can complete in 80 Days C + A can complete in 120 Days Calculation: Taking LCM, total work = 240 (A + B)’

    Home Quantitative Aptitude Time and Work Work Efficiency

    Question

    Download Solution PDF

    A and B can complete a work in 60 days, B and C complete it in 80 days, C and A can complete the same work in 120 days. In how many days, B alone can do that work?

    This question was previously asked in

    TSPSC Group 4 Secretarial Ability Official Paper-II (Held in: 2018)

    Download PDF Attempt Online

    View all TSPSC Group 4 Papers >

    96 90 92 94

    Answer (Detailed Solution Below)

    Option 1 : 96

    Crack TSPSC Group 4 with

    India's Super Teachers

    FREE

    Demo Classes Available*

    Explore Supercoaching For FREE

    Free Tests

    View all Free tests >

    FREE

    CT 1: General Studies(International Relations and Events)

    17 K Users

    10 Questions 10 Marks 10 Mins

    Start Now

    Detailed Solution

    Download Solution PDF

    Given:

    A + B can complete in 60 Days

    B + C can complete in 80 Days

    C + A can complete in 120 Days

    Calculation:

    Taking LCM, total work = 240

    (A + B)’s 1 day work = 240/60 = 4      ---- (1)

    (B + C)’s 1 day work = 240/80 = 3      ---- (2)

    (C + A)’s 1 day work = 240/120 = 2      ---- (3)

    Now, add equation 1 and 2 then subtract 3 from it to get 2 × B’s 1 day work

    ⇒ 4 + 3 – 2 = 5 ⇒ 2B = 5 ⇒ B = 5/2 = 2.5

    ∴ Number of days required = 240/2.5 = 96

    Download Solution PDF

    Share on Whatsapp

    Latest TSPSC Group 4 Updates

    Last updated on Feb 3, 2023

    TSPSC Group 4 Exam Date has been released. The exam is scheduled for 1st July 2023. A total of 8180 vacancies have been released for various TSPSC Group 4 posts like Junior Assistant, Junior Accountant, Junior Auditor, and Ward Officer. The selection process will consist of three stages namely Computer Proficiency Test (CPT), a Personal Interview, and Certificate Verification. With Bachelor’s Degree as the basic TSPSC Group 4 Eligibility Criteria, this is a golden opportunity for aspirants who are preparing for government jobs.

    Ace your Time and Work preparations for Work Efficiency with us and master Quantitative Aptitude for your exams. Learn today!

    India’s #1 Learning Platform

    Start Complete Exam Preparation

    Daily Live MasterClasses

    Practice Question Bank

    Mock Tests & Quizzes

    Get Started for Free

    Download App

    Trusted by 3.8 Crore+ Students

    ‹‹ Previous Ques Next Ques ››

    More Work Efficiency Questions

    Q1. A can do a piece of work in 22 days while B alone can complete the whole work in 26 days. They work together for 5 days then A left the work and remaining work can done by B alone. In how many days will finish the whole work?Q2. 8 masons working 8 hours a day can build a wall in 20 days. If these 10 masons also work for 8 hours a day, then in how many days will 10 masons build the same wall?Q3. X is twice as good a workman as Y and together they finish a piece of work in 22 days. In how many days will X alone finish the work?Q4. Ramu can do a work in 36 days and Kanu in 32 days. If they work on it together for 12 days, then what fraction of work is left?Q5. Punam can do the work in 8 days, while Mona can do the same work in 6 days. Both of them finish the work together and get Rs. 490. What is the share of Punam?Q6. "A" and "B" can do a piece of work in 8 days which "A" alone can do in 12 days. In how many days can "B" alone do the same work?Q7. A and B can do a piece of work in 72 days; B and C can do it in 120 days; A and C can do it in 90 days. In what time can A alone do it?Q8. 10 men do a work in 15 days. 7 men and 3 women do the same work in 20 days. The number of days taken by a woman to do the work isQ9. 16 laborers take 35 days to complete construction. Exactly, how many days will the same work be completed by 28 laborers?Q10. A takes twice as much time as B or thrice as much as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in

    More Time and Work Questions

    Q1. A can do a piece of work in 22 days while B alone can complete the whole work in 26 days. They work together for 5 days then A left the work and remaining work can done by B alone. In how many days will finish the whole work?Q2. 5 men and 3 women together or 9 men can cultivate a land in 60 days. Then how many days 8 men and 9 women together cultivate the same land.Q3. P can do a job in 8 days, Q in 12 days and R in 16 days. How many days are required to finish the work by R, if he is assisted by P and Q on every second day?Q4. 2 men and 3 boys can do a work in 10 days while 3 men and 2 boys can do a work in 8 days. In how many days, can 2 men and 1 boy do the same work?Q5. A and B can finish a work in 30 days, B and C in 40 days while C and A in 60 days. How long will they take to finish it while working all together?Q6. 8 masons working 8 hours a day can build a wall in 20 days. If these 10 masons also work for 8 hours a day, then in how many days will 10 masons build the same wall?Q7. If Aman alone can do a work in 5 days, Sagar alone can do the work in 10 days and Satish alone can do the work in 15 days, then in how many days will they complete 11 such works?

    स्रोत : testbook.com

    A and B can complete a work in 60 days, B and C can complete it in 80 days, C and A can complete the same work in 120 days. In how many days, B alone, can do that work?

    Answer (1 of 9): Solution of the given problem is shown below, * Let W denotes the whole given work. * It is mentioned that * * (i) A & B can complete the work W in 60 days. * (ii) B & C can complete the work W in 80 days. * (iii) C & A can complete the same work in 120 days. * (iv) Let ...

    A and B can complete a work in 60 days, B and C can complete it in 80 days, C and A can complete the same work in 120 days. In how many days, B alone, can do that work?

    Ad by Aspose

    Need a .NET API to perform OCR on images?

    Easily add OCR functionalities in any .NET based applications using our extensible and powerful API.

    Sort Nishav Mehrotra

    Studied at Institute of Management Studies, Noida4y

    Your response is private

    Was this worth your time?

    This helps us sort answers on the page.

    Absolutely not Definitely yes Related questions

    A & B can do a piece of work in 80 days. B & C can do same work in 50 days and C & A can do same work in 60 days. Find in how many days they all together can complete that work?

    A and B can do a work in 60 days, B and C can do a work in 40 days and C and A can do the same work in 50 days. Find in how many days they together can complete the work?

    A and B can do work in 60 days. B and C in 90 days. A and C can work in 120 days. How many days can A also work alone?

    A and B can do a piece of work in 72 days. B and C can do the same work in 120 days. A and C can do it in 90 days. Accordingly, in how many days can A alone do it?

    A can complete a work in 60 days and both b and c can complete it in 10 days then in how many days b alone can do the work?

    Sanjay

    Let's share our knowledge Author has 118 answers and 6.2K answer viewsFeb 3

    Let's solve the problem……..

    (A+B)=60=1/60 (B+C)=80=1/80 (C+A)=120=1/120 Now

    (A+B)+(B+C)+(C+A)=1/60+1/80+1/120

    Or, (2A+2B+2C)=(4+3+2)/240

    Or, 2(A+B+C)=9/240

    Or, (A+B+C)=3/(80×2)

    Or, (A+B+C)=3/160 Now……

    (A+B+C)—(C+A)=3/160–1/120

    Or B=(9–4)/480 Or, B = 5/480 Or, B = 1/96

    So B can finish the work in 96 days.

    If you agree with me please upvote me and follow me.

    Gaurav Pipil

    B.Tech in in Computer Science, Gautam Buddha University (Graduated 2016)4y

    lets assume total amount of work is 240 units.

    A+B one day work will be => 240/60 = 4 units

    B+C one day work will be => 240/80 = 3 units

    C+A one day work will be => 240/120 = 2 units

    Now add above three equations

    A+B+B+C+C+A = 4 + 3 + 2

    2(A+B+C) = 9 A + B + C = 9/2

    put the value of A + C in above equation

    2 + B = 9/2 B = 5/2

    B alone can do the work in 240/(5/2) = 96 days

    ANSWER is :- 96 days

    Sponsored by SmartCredit.io

    We are building the future of decentralized world.

    Join us if you want to explore web3 and learn more about the future of economics.

    Ved Prakash Sharma

    Former Lecturer at Sbm Inter College, Rishikesh (1971–2007)Author has 12.1K answers and 12.1M answer views4y

    let A alone can do a piece of work in x days, B alone in y days. and C alone in

    z days. therefore their one day work will be 1/x,1/y and 1/z respectively.

    Accordingly:-

    1/x+1/y= 1/60…………….(1)

    1/y+1/z= 1/80……………..(2)

    1/z +1/x=1/120………………(3)

    On adding eqn.(1). (2) and (3).

    2.(1/x+1/y+1/z) =(4+3+2)/240=9/240 = 3/80

    1/x+1/y+1/z=3/160……………(4)

    On subtracting eqn.(3) from (4)

    1/y =3/160–1/120 =(9–4)/480=5/480 = 1/96

    1/y=1/96 or. y = 96 days

    B alone can do that work in 96 days. Answer.

    Related questions

    A & B can do a piece of work in 80 days. B & C can do same work in 50 days and C & A can do same work in 60 days. Find in how many days they all together can complete that work?

    A and B can do a work in 60 days, B and C can do a work in 40 days and C and A can do the same work in 50 days. Find in how many days they together can complete the work?

    A and B can do work in 60 days. B and C in 90 days. A and C can work in 120 days. How many days can A also work alone?

    A and B can do a piece of work in 72 days. B and C can do the same work in 120 days. A and C can do it in 90 days. Accordingly, in how many days can A alone do it?

    A can complete a work in 60 days and both b and c can complete it in 10 days then in how many days b alone can do the work?

    A alone can complete a work in 24 days, and B can complete the same work in 40 days. In what days are taken by A and B together to complete 60% of work?

    Two persons A & B can complete a work in 20 days, B & C can complete it in 30 days, while C & A can completed it in 24 days. How many days will B complete the work alone?

    To complete work A takes 6 days and B takes 12 days. After A and B worked for two days, C joined them and they completed the work on the 3rd day. How many days does C alone take to complete the same work?

    A alone can complete a work in 13 days and B alone can complete the same work in 26 days. In how many days can A and B together complete the same work?

    A and B do a work in 72 days, B and C do it in 120 days and A and C do it in 90 days. How many days can A alone do the same work?

    A can do a piece of work in 8 days, B can do the same work in 6 days while A, B and C together can do the same work in 3 days. In how many days can C alone complete the same work?

    A and B can do a certain work in 12 days, B & C can do the same work in 15 days, while A and C can do the same work. In 36 days. In how many days will all three together complete that work?

    स्रोत : www.quora.com

    A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it ?

    Click here👆to get an answer to your question ✍️ A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it ?

    Question

    A and B can do a piece of work in 72 days. B and C can do it in 120 days. A and C can do it in 90 days. In what time can A alone do it ?

    A

    120 days

    B

    150 days

    C

    180 days

    D

    200 days

    Medium Open in App Solution Verified by Toppr

    Correct option is A)

    (A + B)'s 1 days' work =

    72 1 ​ ;

    (B + C)'s 1 days work =

    120 1 ​ ;

    (A + C)'s 1 days' work =

    90 1 ​ ∴(A+B) ′ s+(B+C) ′ s+(A+C) ′ s 1 days work = 72 1 ​ + 120 1 ​ + 90 1 ​ = 360 5+3+4 ​ = 360 12 ​ = 30 1 ​ ⇒2(A+B+C) ′ s 1 days' work = 30 1 ​ ⇒(A+B+C) ′ s = 60 1 ​

    ∴ A's 1 days' work = (A+B+C)'s 1 days' work - (B+C)'s 1 days' work

    = 60 1 ​ − 120 1 ​ = 120 2−1 ​ = 120 1 ​

    ∴ A alone will complete the work in 120 days

    Was this answer helpful?