activities a, b, and c are the immediate predecessors for y activity. if the earliest finishing time for the three activities are 12, 15, and 10, then what will be the earliest starting time for y?
Mohammed
Guys, does anyone know the answer?
get activities a, b, and c are the immediate predecessors for y activity. if the earliest finishing time for the three activities are 12, 15, and 10, then what will be the earliest starting time for y? from screen.
MCQs on PERT and CPM with answers, updated for 2022
Find out the MCQs on PERT and CPM, these multiple choice questions are given with answers for the benefits of the students.
CommerceCommerce MCQsPert And CPM Mcqs
MCQs on PERT and CPM
Programs or Project Management and Review Technique (PERT) is appropriate for those projects where the time required to accomplish different activities are not known. CPM or Critical Path Method is appropriate for the projects that are reappearing (recurring) in nature.
To achieve the end goal of a project on time, PERT and CPM are two project management techniques that every manager should implement.
Here are the essential MCQs given on the PERT and CPM to analyse your understanding of the topic. The answers are also given for your reference.
PERT and CPM MCQs
Question 1What is PERT analysis based on?A. Optimistic time B. Pessimistic time C. Most likely time D. All of the above
Answer: DQuestion 2Which of the options is not a notable challenge while scheduling a project?A. Deadlines exist
B. Independent activities
C. Too many workers may be required
D. Costly delay
Answer: BQuestion 3What is the particular task performance in CPM known as?A. Dummy B. Event C. Activity D. Contract
Answer: CQuestion 4What is the earliest start time rule?A. It compares the activity’s starting time for an activity successor.
B. It compares the activity’s end time for an activity predecessor.
C. It directs when a project can start.
D. It regulates when a project must begin.
Answer: BQuestion 5What is a critical path?A. It is a path that operates from the starting node to the end node.
B. It is a mixture of all the paths
C. It is the longest path
D. It is the shortest path
Answer: CQuestion 6What is the completion of a CPM network diagram activity commonly known as?A. Connector B. Event C. Node D. All of the above
Answer: DQuestion 7Activities A, B, and C are the immediate predecessors for Y activity. If the earliest finishing time for the three activities are 12, 15, and 10, then what will be the earliest starting time for Y?A. 10 B. 15 C. 12
D. Cannot be determined
Answer: BQuestion 8Activities P, Q, and R instantly follow activity M, and their current starting times are 12, 19, and 10. So, what is the latest finishing time for activity M?A. 11 B. 10 C. 18
D. Cannot be determined
Answer: AQuestion 9Activity in a network diagram is represented by?A. Rectangles B. Arrows C. Squares D. Circles
Answer: BQuestion 10What happens when a project is scheduled by CPM?A. A project is divided into various activities
B. Required time for each activity is established
C. A sequence of various activities is made according to their importance
D. All of the above
Answer: DStay tuned to BYJU’S for more MCQs, sample papers, question papers, syllabus and Commerce notifications.
COMMERCE Related Links
Forfeited Shares Limited Liability Partnership
Depreciation Formula Responsibility Accounting
Statistics For Economics Ts Grewal Solutions Class 11
Advantages Of Partnership What Is Entrepreneurship
Bill Of Exchange Format Intermediate Goods
[Solved] The immediate predecessors of activity D are A, B, and C. Gi
Explanation: Earliest Start Time (EST) The earliest start time for an activity is the earliest time by which it can commence. This is naturally equal to the e
Home Construction Materials and Management Project Planning PERT
Question
Download Solution PDF
The immediate predecessors of activity D are A, B, and C. Given the earliest finish time of activity A, B and C are respectively 10, 12 and 16 days, the earliest start time of activity D will be:
This question was previously asked in
JKSSB JE CE 2021 Official Paper Shift 2 (Held on 27 Oct 2021)
Download PDF Attempt Online
View all JKSSB JE Papers >
10 days 12 days 38 days 16 days
Answer (Detailed Solution Below)
Option 4 : 16 days
Crack AE & JE - Civil with
India's Super Teachers
FREE
Demo Classes Available*
Explore Supercoaching For FREE
Free TestsView all Free tests >
FREE
RSMSSB JE General Knowledge Free Mock Test
10.5 K Users
10 Questions 10 Marks 8 Mins
Start Now
Detailed Solution
Download Solution PDF
Explanation:Earliest Start Time (EST)The earliest start time for an activity is the earliest time by which it can commence. This is naturally equal to the earliest event time associated with the tail of the activity arrow. It is abbreviated by EST.
If the activity is denoted i - j, and if the earliest event time at its tail is TiE, we have EST = TiE
Earliest Finish Time (EFT)If an activity proceeds from its early start time and takes the estimated duration for completion, then it will have an early finish. Hence earliest finish time (EFT) for an activity is defined as the earliest time by which it can be finished. This is evidently equal to the earliest start time plus estimated duration of the activity:
EFT = earliest start time + activity duration = TiE + tij
Earliest start time of activity D = Max (All the earliest finish times of activities ending at D)= Max (Earliest finish time of A, B, and C)= Max (10,12, 16)
Earliest start time of activity D = 16 Days.Additional Information
Latest Start Time (LST)Latest start time for an activity is the latest time by which an activity can be started without delaying the completion of the project. For ‘no delay’ condition to be fulfilled, it should be naturally equal to the latest finish time (LFT) minus the activity duration.
∴ LST = LFT - Activity duration = TiL - tij
Latest Finish Time (LFT)The latest finish time for an activity is the latest time by which an activity can be finished without delaying the completion of the project. Naturally, the latest finish time for an activity will be equal to the latest allowable occurrence time for the event at the head of the arrow.
LFT = Latest event time at the head of activity arrow = TiL
Download Solution PDF
Share on Whatsapp
Latest RSMSSB JE Updates
Last updated on Dec 15, 2022
RSMSSB JE Provisional Select List Out! The RSMSSB JE Final Result and Cut Off have been released for written examination held on 14th October 2022. The Rajasthan Subordinate & Ministerial Services Selection Board had announced a total of 189 vacancies for RSMSSB JE (Agriculture). The finally appointed candidates will be entitled to Pay Matrix Level 10.India’s #1 Learning Platform
Start Complete Exam Preparation
Daily Live MasterClasses
Practice Question Bank
Mock Tests & Quizzes
Get Started for Free
Download App
Trusted by 3.8 Crore+ Students
‹‹ Previous Ques Next Ques ››
More PERT Questions
Q1. A dummy activityQ2. Free float is mainly used toQ3. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will beQ4. The total activity slack is equal to:Q5. A dummy activity in a net work:Q6. F. W. Taylor introduced a system of organization known asQ7. The time in which an activity will take to complete in case of difficulty, is called:Q8. Which of the following statement is correct about the net work diagram?Q9. Which of the following statement is wrong?Q10. The start or completion of task is calledMore Project Planning Questions
Q1. Time and progress chart of a construction is known as:Q2. A construction schedule is prepared after collecting:Q3. A dummy activityQ4. In Bar chart method, the activity is indicated alongQ5. Free float is mainly used toQ6. Math List-I (item) with List-II (Characteristics) and select the correct answer using the codes given below the lists: List-I List-II (a) Activity (i) Resourceless element (b) Event (ii) Resources consuming element (c) Dummy (iii) Spare time (d) Float (iv) Instantaneous stageQ7. If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will beQ8. An activity requiresQ9. The process of calculating the resource requirement of a project is known asQ10. Which of the following statement is correct?Solved Question 12 1 pts Activities A, B, and C are the
Answer to Solved Question 12 1 pts Activities A, B, and C are the
Skip to main content
Save 70% off your first month.
For a limited time, save on Chegg Study or Study Pack subscription. Click the "got coupon?" link at Checkout and enter code CHG70OFF. See terms & conditions
Sign Up
Question: Question 12 1 Pts Activities A, B, And C Are The Immediate Predecessors For Y Activity. If The Earliest Finish Times For The Three Activities Are 12, 15, And 10, Then The Earliest Start Time For Y Will Be O 10 O 37 15 O Cannot Be Determined O 12
Show transcribed image text
Expert Answer
100%
Answer: 15 Since activities A, B, and C are the immediate predecessors for Y activity, Y can be start…