    ram and shyam working alone can complete a task in 20 days and 10 days

    Mohammed

    Guys, does anyone know the answer?

    get ram and shyam working alone can complete a task in 20 days and 10 days from screen.

    [Solved] Ram alone can complete a work in 20 days and Shyam alone can

    Given: Ram alone can complete a work in 20 days Shyam alone can complete a work in 15 days Formula: Total work = Efficiency × Time Calculation: Tota

    Home Quantitative Aptitude Time and Work Work Efficiency

    Question

    Download Solution PDF

    Ram alone can complete a work in 20 days and Shyam alone can the same work in 15 days. Ram started the work and after working 3 days, Shyam joined Ram to finish the remaining work. In how many days, the remaining work will be finished?

    51/7 days 53/9 days 63/8 days 51/9 days

    Answer (Detailed Solution Below)

    Option 1 : 51/7 days

    Crack Railway with

    India's Super Teachers

    FREE

    Demo Classes Available*

    Explore Supercoaching For FREE

    Free Tests

    View all Free tests >

    FREE Cell 6.6Lac Users

    10 Questions 10 Marks 7 Mins

    Start Now

    Detailed Solution

    Download Solution PDF

    Given:

    Ram alone can complete a work in 20 days

    Shyam alone can complete a work in 15 days

    Formula:

    Total work = Efficiency × Time

    Calculation:

    Total work = 60 units (LCM of 20 and 15)

    Efficiency of Ram = 3 units/day

    Efficiency of Shyam = 4 units/day

    Work done by Ram in 3 days = 3 × 3 = 9 units

    Remaining work = 60 – 9 = 51 units

    ∴ Time taken by Ram and Shyam remaining work = 51/(3 + 4) = 51/7 days

    Download Solution PDF

    Share on Whatsapp

    Latest RRB NTPC Updates

    Last updated on Sep 21, 2022

    The RRB (Railway Recruitment Board) has released the Result, and Cut Off marks for the CBAT (Computer Based Aptitude Test) stage for Pay Level 6. The result and cut-off marks are announced for the RRB Chandigarh, Bhopal & Chennai regions for the recruitment cycle 2021. The exam is conducted to fill up a total number of 35281 vacant posts. Candidates who are qualified for the Computer Based Aptitude Test will be eligible for the next round, which will be Document Verification & Medical Exam. The candidates with successful selection under RRB NTPC will get a salary range between Rs. 19,900 to Rs. 35,400. Know the RRB NTPC Result here.

    Ace your Time and Work preparations for Work Efficiency with us and master Quantitative Aptitude for your exams. Learn today!

    India’s #1 Learning Platform

    Start Complete Exam Preparation

    Daily Live MasterClasses

    Practice Question Bank

    Mock Tests & Quizzes

    Get Started for Free

    Download App

    Trusted by 3,17,38,724+ Students

    ‹‹ Previous Ques Next Ques ››

    More Work Efficiency Questions

    Q1. If seven persons can build a house in 30 days, how long will it take three persons to build the same house, provided that they all work at the same rate?Q2. A, B and C can complete a work in 12, 16 and 24 days respectively. B and C worked together for 4 days then C left the work and A replaced him. In how many days will the remaining work be completed?Q3. P, Q, R can do a piece of work in 40 days, 90 days and 36 days, respectively. P started the work. Q joined him after 7 days. If R joined them after 8 days from the beginning, then for how many days did R work?Q4. A man can do a work in 20 days and a woman can do the same work in 30 days. In how many days will 2 men and 3 women do the work?Q5. 8 men or 12 women can do a piece of work in 24 days. In how many days can the work be done by 8 men and 12 women?Q6. Ronit and Hrithik can complete a work in 15 days and 35 days respectively. Hrithik started the work alone and joined by Ronit after the completion of

    25

    of the work. Find the time taken to complete the work in this way:

    Q7. 41 girls can complete a piece of work in 40 days. If x girls started the work and after 30 days 64 more girls joined them so that the whole work gets finished in the desired time, find the value of x.Q8. Rajat started a work alone and left after 10 days leaving 75% of the work for Simran. If Simran can complete the remaining work in 30 days, then find the time taken by Rajat and Simran together to complete 45% of the work.Q9. A can do a piece of work in 10 days while B can do the same work in 20 days. They start together but A leaves after three days. How many days will B take to complete the remaining work?Q10. X takes 5 days more than Y and 9 days more than Z to finish a piece of work. X and Y can do a piece of work together in the same time in which the Z alone can do the work. In how many days X finishes the work?

    More Time and Work Questions

    Q1. If seven persons can build a house in 30 days, how long will it take three persons to build the same house, provided that they all work at the same rate?Q2. A, B and C can complete a work in 12, 16 and 24 days respectively. B and C worked together for 4 days then C left the work and A replaced him. In how many days will the remaining work be completed?Q3. Ram and Rahim together have Rs. 1210. If

    13

    of Ram's money is equal to

    25

    of Rahim's amount, then what is the amount (in Rs.) that Rahim has?

    Q4. P, Q, R can do a piece of work in 40 days, 90 days and 36 days, respectively. P started the work. Q joined him after 7 days. If R joined them after 8 days from the beginning, then for how many days did R work?

    स्रोत : testbook.com

    Ram can do a piece of work in 20 days, and Shyam can do it in 30 days. If both of them work together, how many days will it take them to finish the work?

    Answer (1 of 15): Ram is 100 % efficient with his 20 man days each day he produces 5 % as 20 days /100% Shyam is only 50% efficient when compared to Ram , as a result of this Shyam takes 30 man days to complete the same amount of work.each day Shyam produces 3.33 % per day for 30 days Therefore...

    Ram can do a piece of work in 20 days, and Shyam can do it in 30 days. If both of them work together, how many days will it take them to finish the work?

    Ad by Amazon Web Services (AWS)

    AWS is how.

    AWS removes the complexity of building, training, and deploying machine learning models at any scale.

    Sort Alok Karande

    Interest in Solving puzzles/riddlesAuthor has 567 answers and 1.5M answer views2y

    Related

    Ram can do work alone in 20 days and Shyam can do this work in 30 days. How much work can they do together in 6 days?

    In a day if Ram and Shyam work together they will complete 1/20 + 1/30 portion of the work. In 6 days it will be 6(1/20 + 1/30) = 1/2 or half the work.

    Related questions

    Ram can do work alone in 20 days and Shyam can do this work in 30 days. How much work can they do together in 6 days?

    A and B together can do a piece of work in 30 days. A worked for 16 days, B finished the remaining work alone in 44 days. In how many days shall B finish the whole work alone?

    Ram completed a piece of work in 25 days, and Shyam in 20 days. If Ram and Shyam work together for 5 days, and then Ram goes away, how many days will it take Shaym to complete the work?

    Ram can do a piece of work in 20 days while Shyam can do it in 15 days with, and with the work of Aman they finish the work in 5 days . In how many days could Aman alone do it?

    Ram, Shyam, and Mohan can do a piece of work in 12, 18, and 30 days respectively. How long will they take to finish it together?

    Richard Roberts

    Dog walkerAuthor has 1.3K answers and 392K answer views1y

    Ram can do a piece of work in 20 days

    Ram can do 1/20 of a piece of work in 1 day

    Shyam can a piece of work in 30 days

    Shyam can 1/30 of a piece of work in 1 day

    Together they can do

    1/20 + 1/30 of a piece of work in 1 day

    = 3/60 + 2/60 = 5/60

    =1/12 of a piece of work in 1 day.

    They can complete it in 12 days.

    Sponsored by JetBrains

    JetBrains Space is a complete software development platform.

    Everything you need to develop software. Host git repos, review code, automate CI/CD, and use chats.

    Bablu Mardi

    B.Tech (Electrical Engg.) from National Institute of Technology.Author has 393 answers and 191.6K answer views1y

    Ram one days work=1/20

    Shayam one days work =1/30

    According to question both work together.

    1/20+1/30=5/60 =1/12 days

    They finished the work in 12 days.

    Louis M. Rappeport

    B.S. from University of California, BerkeleyAuthor has 6.9K answers and 4.8M answer views1y

    12 days

    20 x 30/20+30=600/50=12

    Let R be Ram, and S be Shyam. Then:

    20R=1 30S=1 60R=3 60S=2 60(R+S)=3+2=5 12(R+S)=1

    Ram and Shayam take 12 days, working together ……………..

    Related questions

    If A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days, how long would it take them to do the same work separately?

    Ram, Shyam and Hari can do any work in 20, 30 and 40 days respectively. All started working together but Ram left after 5 days. If Shyam left 10 days before the end of the work and Hari finished the rest of the work, in how many days?

    A and B can complete a job in 30 and 20 days respectively. They start working together and B leaves 5 days before the work is finished. In how many days is the total work finished?

    Ram can do a piece of work in 10 days and Sham can do the same work in 20 days. Sham works alone for 8 days and later Ram joins him. Together they complete the remaining work in how many days?

    Ram and Shyam complete a work in 6 days. Ram does the work for 4 days and leaves then Shyam completes the remaining work in 9 days. In how many days will Ram complete the work alone?

    Isabelle South 4y

    Ram takes 20 days to do one bit of work. So, he is working at a rate of 1/20 of work per day.

    Shyam takes 30 days to do one bit of work. So, he is working at a rate of 1/30 of work per day.

    Together, both are completing 1/20 and 1/30 of the work. 1/20 + 1/30= 5/60 = 1/12 (cross multiplication method).

    Therefore, their rate together is 1/12 of the work per day. So, it will take them 12 days in total.

    Answer: 12 days Edwin Koh

    Author has 912 answers and 1.5M answer views4y

    Ram takes 20 days to complete a piece of work.

    Shyam takes 30 days to complete a piece of work.

    Ram completes (1/20) of a piece of work in 1 day.

    Shyam completes (1/30) of a piece of work in 1 day.

    Together R and S complete (1/20) + (1/30) = (1/12) of a piece of work in 1 day.

    (1/12) of a piece of work - 1 day

    (12/12) of a piece of work - (12/12)/(1/12) = 12 days.

    R and S take 12 days to complete a piece of work when they work together.

    Sponsored by Autodesk-US

    Looking for the best way to learn AutoCAD?

    Get 6 free months of CADLearning with your Autodesk AutoCAD annual subscription.

    Der Tery

    Author has 97 answers and 386K answer views4y

    Ram takes 20 days Shyam takes 30 dyas

    Ram is 50% quicker than Shyam and therefore would do 60% of the work.

    20X60%=12

    So it would take 12 days if they worked together.

    Haresh Sagar

    Studied Science & Mathematics (Graduated 1988)Author has 3.8K answers and 2.1M answer views2y

    Ram completes his work in 20 days.

    स्रोत : www.quora.com

    Ram can do a piece of work in 20 days, while Shyam can do it in 30 days . If both of them work at it together , in how many days will they be able to finish the work?

    Click here👆to get an answer to your question ✍️ Ram can do a piece of work in 20 days, while Shyam can do it in 30 days . If both of them work at it together , in how many days will they be able to finish the work?

    Question

    Ram can do a piece of work in 20 days, while Shyam can do it in 30 days. If both of them work at it together  , in how many days will they be able to finish the work?

    Easy Open in App

    Updated on : 2022-09-05

    given that:

    Solution Verified by Toppr Ram's efficiency = 20 1 ​ =5%

    Shyam's efficiency =

    30 1 ​ =3.33% Total work =100%

    If both work together then efficiency =5+3.33=8.33%

    Let Ram and Shyam finishes a work in x days then

    x= 8.33 100 ​ x=12

    If both of them work at it together , in 12 days they will be able to finish the work.